The rehabilitated road establishes a connection between County Road 106A and the chairlift area at the base of the Oncești slope. The works included:
– Replacement of the water network
– Repair works for the road surface, sidewalks, paths, and parking areas
– Arrangement of accesses and side roads
– Demolition of the existing supporting wall made of stone and construction of a new wall over a length of 200 meters
– Installation of a new public lighting system with LED fixtures – 140 new poles installed along the road
– Arrangement of a new underground power supply network to eliminate overhead cables. The new network was equipped with devices that allow connection to the city’s lighting management system.